Bond Progress and Events
Groundbreaking Ceremony - May 18, 2011 - 3:00 p.m.
There will be a groundbreaking ceremony on May 18, 2011 at 3:00 p.m. at the football stadium for the bond projects that will be taking place over the summer. Public is welcome to attend.
| Date | Event |
| 2/16/11 | Bond Steering Committee Meeting |
| 2/16/11 | Shoreline Roof Bid Opening |
| 2/16/11 | Design Team Meetings |
| 2/3/11 | Shoreline Roof Pre-Bid Meeting |
| 1/19/11 | Bond Steering Committee Meeting |
| 1/3/11 | All Phase I Technology Installed (48 rooms) |
| 12/15/10 | Bond Steering Committee Meeting |
| 12/15/10 | Design Team Meetings |
| 11/16/10 | Building Tech Walkthrouhs - Shoreline |
| 11/10/10 | Building Tech Walkthroughs - HS, MS, Ealy |
| 10/20/10 | Bond Steering Committee Meeting |
| 10/18/10 | Tech Committee Meeting |
| 10/4/10 | Design Team Meetings |
| 9/27/10 | Board Meeting - AVI SPL Tech Bid Approved |
| 9/21/10 | Technology Committee Meeting |
| 9/13/10 | Bond Steering Committee Meeting |
| 9/13/10 | Tech Bid Opening |
| 8/26/10 | Design Team Meetings |
| 8/25/10 | Tech Pre-Bid Meeting |
| 8/23/10 | 175 Computers Installed |
| 7/23/10 | Staff Survey #4 - Interest on Year 1 Technology Implementation |
| 7/21/10 | Bond Steering Committee Meeting |
| 7/19/10 | Board Approves First Tech Bond Purchase |
| 7/14/10 | Architect and Construction Manager Meet with Superintendent |
| 7/14/10 | Technology Committee Meeting |
| 6/23/10 | Bond Steering Committee Meeting |
| 6/15/10 | Building walkthroughs to determine room technology configurations |
| 6/14/10 | Building walkthroughs to determine room technology configurations |
| 6/2/10 | Staff Survey #3 - re: summer work/involvement |
| 6/1/10 | Technology Committee Meeting - Elementary and Secondary |
| 5/20/10 | Tech Committee visits Montague to discuss implementation ideas |
| 5/18/10 | Staff Survey #2 on Technology Portion of the Bond Initiated |
| 5/18/10 | Architect and Construction Manager Meet with Superintendent |
| 5/18/10 | Architect and Construction Manager Visit Shoreline Elementary |
| 5/17/10 | Technology Committee Meeting - Secondary |
| 5/12/10 | Staff Survey #1 on Technology Portion of the Bond Initiated |
| 5/11/10 | Technology Committee Meeting |
| 5/4/10 | Bond Passes |
2010 Bond Information documents
bid information